PHONE CALL FROM SS TODAY


I spoke with our Site Supervisor (SS) today. The rough plumbing for the bathrooms, kitchen and laundry should be put in this week.

Bricks will be delivered next week and hopefully getting laid. The brickies are running behind on schedule due to all the rain in the last few weeks. So there may be delays.

 The plumbers still can't find the fresh water pipe running past our block. I have to get maps from Sydney Water tomorrow. Lets hope they are locatable.